Cherry Creek Anglers - Trout Unlimited Chapter 474
Trumbull Habitat Improvement/Handicap Access
PROJECT DESCRIPTION - February 6, 2008
OVERVIEW
As part of Cherry Creek Angler’s mission to conserve, protect and
restore Colorado’s coldwater fisheries and their watersheds, for
improvement of the resource and the enjoyment of present and future
anglers, the chapter has initiated a new project that directly
contributes to these objectives.
Our plan is to construct a handicap/wheelchair accessible path along
the bank of the river to provide a quality river fishing experience for
people with impaired abilities. In addition to the path, we plan to
make significant improvements in the river channel of the river to
maximize its trout holding capabilities. The site is near Trumbull,
downstream from Deckers on the South Platte River.
We believe this activity contributes directly to the Conserving and
Sustaining priorities of Trout Unlimited through improving the river
and providing a new recreational resource for an underserved portion of
our community.
The general timetable for the completion of the project is spring,
2010. We expect this will provide adequate time for fundraising, design
and engineering, marshalling of volunteer labor for work on-site, and
actual construction A detailed project plan using this target date has
been developed and is presently in use.
We do not yet have a defendable cost estimate for the project. However,
a preliminary survey of the site will be conducted during February,
2008 to produce a preliminary cost estimate. After that, we will be
seeking funding in the range of $15,000 to support the development of a
full engineering plan for the site.
HISTORY
As Cherry Creek Anglers (CCA) became more fully established as a
chapter of Trout Unlimited, its board of directors began discussions
about projects that might be undertaken to contribute to our community
and to the goals established by Trout Unlimited.
One idea that gained immediate interest was construction of a
river-based handicapped angler’s paved path on a nearby trout
stream. While many stillwater lakes and ponds have areas where a
wheelchair-bound angler can fish, there is only one known site within
100 miles of the Denver area where such access is available along a
river. (This is a site on the Big Thompson River above Loveland, CO. It
is a timber structure around 50 yards long with a steep ramp leading to
the water from the parking area.)
As a result of these discussions, a meeting was arranged with Denver
Water to explore construction of such a facility along the South Platte
River in Waterton Canyon on the outskirts of Denver. The site was
agreed to be very promising, but Denver Water is planning a major
dredging project at Strontia Springs reservoir six miles upstream from
the site, and expects that there will be heavy construction work along
the river for the next two or three years.
However, Denver Water’s Manager of Properties and Recreation
suggested that a site further upstream might be found that is also on
Denver Water property.
We reviewed a number of potential sites in November 2007 and presented
a site and plan outline to Denver Water. In late December, 2007 we were
delighted to receive enthusiastic permission from Denver Water to begin
development of the Trumbull Habitat Improvement and Handicap Access
project on the South Platte River near from Trumbull, Colorado.
The site for the project is approximately one-half mile downstream from
the bridge at the village of Trumbull, or approximately three miles
downstream from Deckers. This area is located in a gentle canyon
stretch of this Gold Medal fishery, with easy access from Denver and
Colorado Springs. It is a beautiful location with the river curving
slightly away from the access road for most of its length.
The character of the river bank, coupled with a channel that currently
holds virtually no fishholding structure, make this an excellent site.
The gradient is moderate and will lend itself very well to construction
of a safe, easily navigable path along the river. At the same
time, the streambed lends itself to installation of habitat
improvement features will benefit the aquatic environment and the rich
potential of the site for providing productive fishing.
The South Platte River is world famous for its trout fishing and
abundant food base that provides strong, healthy fish. A wide variety
of insect species are found in the river – crane flies, mayflies,
a growing caddis population, and terrestrial insects all contribute a
smorgasbord of food for trout. It is a wonderful site to have available
for this project.
Here is an overhead view of the site, based on an image from Google Earth:
THE PAVED WHEELCHAIR PATH
The river is accessible from the South bank, which is where the path
will be constructed. (The black line represents the path. The green
line is an artifact from the Google image.)
The site has not yet been accurately surveyed, but the paved path,
including a section from the parking lot to the river, is expected to
be around 500 feet in length and between four and six feet wide. Denver
Water is planning to install a handicapped-usable restroom near the
edge of the parking lot in 2008. The rectangular area near the center
of the path will contain a simple ramada, or shaded area, for use by
the anglers.
There will be between six and eight turnouts along the route where
wheelchairs can be conveniently parked at the river’s edge
without obstructing traffic. Each turnout will be equipped with a
railing to prevent accidental spills into the water. The rails will be
low enough to allow easy casting and landing of fish, while high enough
to prevent accidents. A small ramp will be provided at each station to
allow an angler’s companion to release fish at the water’s
edge to reduce injury. The width of the path will allow passage
of wheelchairs in both directions.
While the nature of the surfacing of the path is not yet finally
established, we envision that concrete will be the material of choice
so that maintenance will be minimized. Concrete is also desirable from
the perspective of anchoring the path railings and allowing a low curb
to be integrated into the river side of the route. However, all
materials will be explored as part of the engineering process to make
the optimal choice.
THE RIVER
The river, in the image from Global Earth, is partially obscured
– the shot was apparently made in the winter, and there is an
accumulation of ice in the water.
From the point where the access trail meets the water on the left end
of the area, to the small island near the end of the trail, the
riverbed has little structure. However, it has a solid bottom and
appears to lend itself well to the installation of various fish-holding
structures that will improve the habitat’s ability to hold a
substantial trout population.
While it is too early in the planning to be specific about the
in-stream work, it is expected that the project will involve bank
stabilization, possibly with gabions, on the north shore, the use of
boulders and timbers to create rips and eddies, and possibly deepening
of the channel in some locations.
From the point of the island to the river’s intersection with the
road, the channel deepens and has good fish holding characteristics;
this area should require little, if any, improvement work.
THE PLAN
A compressed version of the overall project plan is shown below. This
version is very tentative as the planning process is just beginning at
this time.
Key milestones for 2008 include:
- Identifying and recruiting key personnel for specific roles in the project.
- Completing the preliminary site survey
- Obtaining sufficient funding for a detailed site survey,
preliminary design, and accurate cost estimate. (Informal estimate is
around possibly $15,000.00)
- Conducting the detailed site survey, design, and costing exercise.
- Begin recruiting key funding sources for the balance of the project.
As the project progresses more detail will be added to the plan and
individual resources will be identified. A critical part of the process
in all phases will be continuing liaison with Denver Water to assure
the project meets with their approval.
This project will be a combined effort led by CCA, but with expected
participation by Denver Water, the Colorado Division of Wildlife, the
U. S. Forest Service, business, and organizations dedicated to river
conservation and assisting the disabled.
CONTRACTORS/VOLUNTEERS
CCA will solicit volunteer assistance on the project from our chapter
membership and all other available sources. However, in order to
establish an accurate estimate of costs, we presume that contractors
will be selected through a review and bidding process to perform all or
most of the following tasks.
- Survey and engineering of the paved path
- Survey and engineering of the river channel improvement work
- Construction and installation of river channel structures
- Building concrete forms for the paved path and ramada floor (partial)
- Construction of the ramada structure (partial)
- Pouring and finishing of the paved path
- Installation of curbs, safety rails, and fish-return ramps
CCA expects to provide volunteer supervision of the project, as well as
volunteer labor along with others from interested organizations and
individuals, in the following areas:
- Preliminary survey (all)
- Site preparation – vegetation removal and hand grading (all)
- Installation of concrete forms (partial w/contractor)
- Post-construction site cleanup (all)
- Planting of riparian vegetation (all)
- Installation of signage (all)
MATERIALS
Every effort will be made to obtain materials on a donation or heavily
discounted basis to help control costs. The required concrete, lumber,
and roofing materials will be solicited from Denver and Colorado
Springs area suppliers. Materials for the river channel improvement may
also be available on a donated or discounted basis; this potential will
be fully explored.
FINANCING
It is expected that donations and volunteer labor from CCA members and
other interested parties will offset a substantial part of the cost of
the project.
To acquire the necessary financing for the balance, CCA is forming a
funding task force to market the project to a variety of potential
sources. This activity is currently in the organization and development
phase; its critical path predecessor is the site survey and preliminary
cost analysis that will give us a credible message to potential donors.
There are two phases to the program once launched: 1) Acquisition of
the estimated $15,000.00 to initiate and complete the engineering and
design phase of the project. Target date – September, 2008,
and 2) Acquisition of the balance of the funding needed to complete the
construction of the project.
It is extremely encouraging that, at this early point in the project,
several interested organizations have voluntarily come forward
expressing interest in participating in both the financing and
implementation of the project.
All funding for the project will be dedicated to its completion.
Detailed accounting of all expenditures will be maintained to assure
proper management of the dedicated funds. A detailed budget will be
prepared as soon as cost estimates are available. This budget will be
integrated into the presentation package prepared for potential donors
of cash, services, and materials.
OUTREACH
Pursuit of this project has been approved by Cherry Creek
Angler’s Board of Directors with the clear understanding that it
will require vigorous outreach to the chapter’s membership and
many external organizations to insure a successful completion.
This outreach will involve establishing and maintaining close relations and communications with:
- Denver Water – review and approval of design and implementation of the facility.
- Department of Wildlife – review and comments on habitat improvements.
- U.S. Forest Service – endangered species considerations
- Other TU chapters – ideas, advice, assistance in development of the project
- Organizations for the Disabled - ideas, advice, assistance in development of the project
- Sources of Donations and Grants – provision of funding
- Communications Companies – radio, tv and press for
publicity about the project to help our outreach for funding and
volunteers.
As the phrase goes, ‘to list is to limit’. Other areas of
outreach will present themselves as the project moves forward.
SUMMARY
The Trumbull Habitat Improvement/Handicap Access project represents a
major commitment by Cherry Creek Anglers in providing a recreational
resource to an underserved part of the Front Range community.
In addition to providing a unique opportunity for handicapped anglers,
the project will contribute to the overall health of the South Platte
watershed by significantly improving the aquatic habitat in an area
that is currently sub-par for the river.
We welcome participation and support from all interested parties.
For further information contact Berle Larned, Conservation Committee
Chair, Cherry Creek Anglers – 720-870-3836 –
berlestu@comcast.net
Below is more information:
Return
To Home Page
